2005 EEP FULL-DELIVERY PROGRAM AWARDS
Project
Name
|
Basin
|
RFP
# |
Cat.
Unit
|
Firm
|
Mitigation
Units
|
Contract
Amount |
Ballance Site
|
Neuse
|
16-D05020
|
03050105
|
Buck Engineering
|
50.0 Buffer
|
$2,050,000.00
|
Beaverdam Creek
|
Catawba
|
16-D05016
|
03050101
|
River Works
|
12,973 Stream
|
$2,983,790.00
|
Big Bull Creek
|
Neuse
|
16-D05015
|
03020201
|
Restoration
Systems
|
35.0 Buffer
|
$980,000.00
|
| Black Gum Creek |
Lumber |
16-D05019 |
03040203 |
Louis Berger Group |
10,000 Stream |
$2,010,000.00 |
| Blounts Creek |
Cape Fear
|
16-D05013
|
03030004
|
CH2M Hill
|
7,999 Stream
|
$2,195,165.57
|
| Brogden Road |
Neuse
|
16-D05015
|
03020201
|
Restoration Systems
|
15.0 Buffer
|
$420,000.00
|
| Brown Farm |
Cape Fear |
16-D05011 |
03030002 |
KCI Technologies |
25.2 Riv WL |
$1,638,260.00 |
| Collins Creek |
Cape Fear |
16-D05011 |
03030002 |
KCI Technologies |
10,799 Stream |
$1,889,825.00 |
| Conetoe Creek |
Tar-Pamlico
|
16-D05026
|
03020103
|
Restoration Systems
|
10.0 Buffer
|
$194,000.00
|
| Conoconnara Swamp |
Roanoke
|
16-D05024
|
03010107
|
EBX
|
5,000 Stream; 87.0 NRiv WL
|
$3,791,300.00
|
| Daniels Farm #2 |
Tar-Pamlico
|
16-D05025
|
03020101
|
KCI Technologies
|
15.0 Riv WL
|
$525,000.00
|
| Gatlin Swamp |
Roanoke
|
16-D05024
|
03010107
|
Restoration
Systems
|
125.0 NRiv WL
|
$1,875,000.00
|
| Glen Raven Site |
Cape Fear |
16-D05011 |
03030002 |
KCI Technologies |
3,757 Stream |
$1,070,745.00 |
| Gray Farm |
Catawba
|
16-D05016
|
03050101
|
Restoration Systems
|
7,610 Stream
|
$2,199,290.00
|
| Harrell Site |
Tar-Pamlico
|
16-D05025
|
03020101
|
KCI Technologies
|
8,238 Stream
|
$1,466,364.00
|
| Harrell Site |
Tar-Pamlico
|
16-D05025
|
03020101
|
KCI Technologies
|
15.0 NRiv WL
|
$480,000.00 |
| Howard Farm |
Neuse
|
16-D05020
|
03020203
|
Land Management
|
26.3 Buffer
|
$426,060.00
|
| Little Buffalo |
Neuse
|
16-D05015
|
03020201
|
Restoration Systems
|
27.0 Buffer
|
$594,000.00
|
| Little Contentnea III |
Neuse
|
16-D05020
|
03020203
|
Greene Environmental
|
54.16 Buffer
|
$1,098,852.24
|
| Manning Farm |
Tar-Pamlico |
16-D05026 |
03020103 |
Land Management |
10.0 Buffer |
$148,000.00 |
| Moccasin Creek |
Neuse |
16-D05015 |
03020201 |
Greene Environmental |
20.2 Buffer |
$427,815.80 |
| Modlin Site |
Roanoke |
16-D05024 |
03010107 |
Albermarle Restorations |
40.0 Riv WL |
$1,400,000.00 |
| Pleasant Hill Farm |
Neuse |
16-D05021 |
03020203 |
Land Management |
25.0 Buffer |
$392,500.00 |
| Randleman Lake |
Cape Fear |
16-D05012 |
03030003 |
Buck Engineering |
90.0 Buffer |
$3,600,000.00 |
| Reeds Creek |
Catawba |
16-D05016 |
03050101 |
Mid-Atlantic Mitigation |
5.3 Riv WL |
$378,950.00 |
| Silver Creek-Queen |
Catawba |
16-D05016 |
03050101 |
Wetlands Resource Ctr |
4,520 Stream |
$1,050,448.00 |
| Simpson Site |
Tar-Pamlico |
16-D05027 |
03020104 |
Wetlands Resource Ctr |
45.0 Buffer |
$825,660.00 |
| Simpson Site |
Tar-Pamlico |
16-D05027 |
03020104 |
Wetlands Resource Ctr |
30.0 NRiv WL |
$494,400.00 |
| Tarlton Site |
Cape Fear |
16-D05013 |
03030004 |
Mid-Atlantic Mitigation |
3,800 Stream; 8.0 Riv WL |
$1,218,200.00 |
| Whitley Site |
Neuse |
16-D05015 |
03020201 |
EBX |
27.5 Buffer |
$976,250.00 |
Return
to:
Design,